Status Reports

Status Reports

 

Swiftlight’s status reporting functionality allows you to quickly and easily produce a standard Status Report commenting on progress and any issues in your project. An example of a Status Report template is shown below:

 

  1. The top section of the Status Report notes the date of the Status Report, the dates of the previous and next Status Reports (if relevant) and the project sponsors and the project leaders
  2. The next section provides a space for text to describe progress and to highlight any issues you want to raise with the recipients of the report.
  3. The "Progress on Current Activity Groups" section provides summary information on the progress of Activity Groups that are underway or that you have selected to comment on. For each Activity Group, you can update the percentage complete, start and end dates, and status columns, and also make specific comments in the right hand “Comments / Action Taken” column.
  4. The next section provides summary information about Milestones that were due on or before the report date, and then in the subsequent section similar information about Milestones that will fall due before the next report date. For each Milestone, you can update the actual or expected delivery dates, and you can also make specific comments by Milestone in the right hand “Comments / Action Taken” column.
  5. The last section provides a space for any other comments that don’t fit into the above sections

 

Status Reports can be created from the File > Reporting menu.

Before you create your first report, you will be asked to set project baseline dates, which are the dates of Activity Groups and Milestones in your original plan (i.e. the baseline plan when you started the project). With the baseline dates set, you can look at and report on how you are currently doing relative to your baseline in Timeline review mode and through the Status Reports.

Status Reports can be used by themselves or in combination with outputs from other views (e.g. Timeline in review mode, Activity Group Summary, Issue Log, etc.) to provide a rich set of materials for reporting.

When the Status Report is saved, either in draft or final form, all the changes made in the Status Report are carried through to the rest of the file (e.g. changes to Activity Group start / end dates are reflected in the Timeline, Activity Group Detail views etc).

 

Creating a Status Report

Creating a Status Report is very simple. Follow the steps below:

  1. Open the new Status Report dialogue by selecting Reporting > New Status Report from the main menus. (Set the project baseline dates if necessary).
  2. Work through the three simple steps in the “new Status Report” dialogue screens (as below) to select dates for the report, and which Activity Groups and Milestones you want to report on. The dialogues will be pre-populated with the expected items so this should be very straightforward.
  3. Update the status of Activity Groups and Milestones and add your comments in the Status Report template as necessary.
  4. Save your Status Report. When the Status Report is saved the updated information about the Activity Groups and Milestones will be reflected automatically in other views such as the Timeline so that the plan is kept up-to-date.

 

New Status Report Dialogues

Step One:

On selecting Reporting > New Status Report, after an introductory screen, you will see the dialogue below:

 

In this dialogue you can:

  • Select the date for this and the next Status Report using the calendars. Note: if you don’t want to set a next report date, tick the box under the right hand calendar
  • Select the date of the previous report (if any). Swiftlight will use the most recent Status Report in the file (if any) for the "previous report date". If you want to select a different previous report date, you can use the drop down calendar. If this is the first report, or you don’t want to indicate the previous report date, then tick the "this is the first report" box to the right of the drop down calendar
  • List the project sponsor(s) and the team leader(s) in the bottom two boxes

When you are satisfied with your selections, click on the “Next” button to get to Step Two. Note: you can always come back to edit your selections later.

 

Step Two

: you will now see the dialogue below, in which you can choose the Activity Groups that you want to report on.

 

The right hand “Included” box shows Activity Groups that Swiftlight has pre-selected for inclusion in the Status Report, based on the fact that the Activity Group is either underway, or should have been completed since the previous Status Report. The left hand “Excluded” box lists all the other Activity Groups.

If you click to select an Activity Group in either the “Included” or “Excluded” boxes, then various details on it appear underneath (e.g. its name, start and end dates and who is responsible).

To move an Activity Group from “Included” to “Excluded” (or vice versa), select it and then either double click on it, or click on the relevant arrow between the two boxes.

You can also change the order in which “Included” Activity Groups will appear in the Status Report by selecting them and using the arrows to the right of the box to move them up or down.

When you are satisfied with your selections, click on the “Next” button to get to Step Three. Note: you can always come back to edit your selections later.

 

Step Three

: you will now see the dialogue below, in which you can choose the Milestones that you want to report on.

There are two sections in this dialogue: 1) at the top, for “Due / Achieved Milestones” that were due to be completed between the dates of the last and the current Status Report; 2) at the bottom, for “Upcoming Milestones” that will fall due before the expected date of the next report.

 

The right hand “Included” boxes show Milestones that Swiftlight has pre-selected for inclusion in the Status Report, based on their dates and the dates of the previous, current and future Status Reports (if any). The left hand “Excluded” boxes list all the other Milestones. If you click to select a Milestone in either the “Included” or “Excluded” boxes, then various details on it appear underneath (e.g. its name, when it was / is due, who is responsible, and to which Activity Group does it belong).

To move a Milestone from “Included” to “Excluded” (or vice versa), select it and then either double click on it, or click on the relevant arrow between the two boxes.

You can also change the order in which “Included” Milestones will appear in the Status Report by selecting them and using the arrows to the right of the box to move them up or down.

When you are satisfied with your selections, press “Finish” to open up the Status Report template, which you can then go on to update and complete.

 

Updating and Completing the Status Report

After clicking on “Finish”, the Status Report template will appear populated with the Activity Groups and Milestones that you have selected. You can now update the data, add comments etc as needed.

If you want to edit your selections of Activity Groups or Milestones (or the report dates, project sponsor(s), team leader(s)), you can use the right click menus (illustrated below) to get back to the set-up dialogues. If you right click over the Activity Group section of the Status Report, you get the dialogue below.

 

In this right-click menu:

  • If you click on “Add / Remove / Reorder Activity Groups”, the dialogue in Step Two of the “New Status Report Dialogues” is shown which allows you to update your selection of Activity Groups.
  • If you click on “Change report dates”, the dialogue in Step One of the “New Status Report Dialogues” is shown which allows you to update your selection of report dates, project sponsors and team leaders.
  • You can also save the report as a draft, finalise it or print or export it

If you right click over the Milestone section of the Status Report, you will get a similar dialogue to the one above, but with an option to “Add / Remove / Reorder Milestones” which will open up the dialogue in Step 3 of the “New Status Report Dialogues” and allow you to update your selection of Milestones.

When you have completed your edits to the Status Report, you can use the right click menu to save the report as a draft or to finalise it, or you can click on the icon for another view (e.g. to move to the Timeline), in which case the dialogue below opens up which allows you to finalise the report, save it as a draft, or discard all changes.